ITS under AMLAR, Art. 41(2). Status: AMLA final draft published (as at 3 July 2026).
Format for AMLA to refer potential criminal matters to the European Public Prosecutor's Office.
Dates
- Statutory deadline
- 27 June 2026. This is the date written in the Level 1 article.
- AMLA target
- Not recorded.
- Applies from
- Set by the adopting act; not yet recorded.
A draft or final report from AMLA is not law. A technical standard applies only after the Commission adopts it and it is published and starts to apply.
Legal basis
Mandate: ITS by AMLA. Register entry amlar-41-2-its.
Versions and sources
- 3 July 2026: final report — AMLA reporting to EPPO